On any permitted addition, remodel, or new home, there is a point where the structure is fully built but the walls are still open. That is when the building department does its rough framing inspection, and it is one of the most important stops in the whole project.
When it happens
The framing inspection comes after the foundation inspections and before insulation and drywall. Building departments around the area describe the timing in similar terms. Boulder County's current code amendments (Section 110.3.4) say it is made after the roof deck or sheathing, all framing, fireblocking, draftstopping, and bracing are in place, concealed pipes, chimneys, and vents are complete, and the rough electrical, plumbing, mechanical, and heating work is approved. Superior's addition guide describes it as following installation of the roof, framing, fire stopping, sheathing, draft stopping, bracing, and fasteners.
In unincorporated Boulder County, rough plumbing, mechanical, gas, and electrical inspections are made before anything is covered and before the framing inspection. Golden likewise asks for rough plumbing, heating, and electrical inspections to be done before the frame inspection is requested. The order varies by town, so the permit card is the guide.
What the inspector checks
The inspector checks the work against the code and the approved plans. Items the local guides name include:
- all framing, including the roof deck or sheathing
- sheathing, bracing, and fasteners
- pipes, chimneys, and vents that will be concealed
- fire blocking and draft stopping in concealed spaces
- completed interior partitions, subfloor, and stairs, which Golden lists
- repairs to framing cut or damaged by other trades, which Golden also calls out
Engineered parts get special attention. Boulder County's Required Inspections handout asks for the design and layout of trusses or wood I-joists to be on site at the framing inspection, including the signed and sealed truss sheets when engineered trusses are used.
Why the approved plans matter
Boulder County's code requires the approved plans to be kept at the site of work and open to the inspector, and changes that don't match those plans must be resubmitted for approval. Work may not move past an inspection point without the building official's approval, and any portion that does not comply must be corrected and may not be covered until the building official authorizes it.
Some structural inspections can come from an engineer instead of the building department. Boulder County allows a qualified, state-licensed engineer to inspect caissons, footings, foundation walls, and structural framing, with a signed and sealed report submitted before the rough inspections.
What comes next
Once framing passes, insulation goes in, followed by an insulation inspection. In unincorporated Boulder County, projects over 500 square feet of conditioned floor area need an approved third-party energy rater for that inspection; for 500 square feet or less, the building official performs it on request. Drywall follows, and some jurisdictions inspect it before taping. The final inspection closes out the permit.
If the inspector finds corrections, they must be made before that work is covered. Boulder County may also charge a re-inspection fee when a site is not ready for a scheduled inspection. Either way, framing is far easier to fix while the walls are still open.